JOHNS PLACE ESTATE

We were requested to remove the existing 23 meter high chimney and flue system serving communal boilers on Johns Place Estate for Tower Hamlets Homes.

During the dismantling of the chimney, we installed a temporary boiler system to maintain heating and hot water services to the estate.

A new 23 meter chimney weather shield was installed with two new flues which were reconnected to the existing communal boilers on completion of works.

All works completed on 8 week programme with minimal disruption to residents and surrounding properties.